海翔航务是一家2009年组建的航务工程施工企业

专业从事码头、防波堤、护岸、堆场道路、船坞、船闸、水下地基及基础、土石方、人工岛、河海航道整治、水下炸礁等港口与航道工程。

福建福清核电一期工程北护堤工程

【概要描述】北护堤总长度为1921米,为斜坡式抛石防波堤,地基采用水下爆破挤淤处理,底部宽度60米,上部宽度7米,施工水深7米,顶部为现浇防浪胸墙,内外侧护面人工护面块体(2t及3t扭王字块体),该工程堤心石共计220万方;爆破挤淤147万方;C40混凝土共计6.7万方。开、竣工时间:2008年8月30日至2011年3月11日。

Northern revetment project for Fujian Fuqing nuclear plant

The total length of the north dike is 1921m. It is a slope-type riprap breakwater. The foundation is formed by underwater silt squeezing by blasting. The bottom width is 60m, the upper width is 7m, and the construction water depth is 7m. The top is cast-in-place anti-wave breast wall, and the inner and outer surface protection is artificial armour blocks (2t and 3t accropode blocks). The core stones of the project is total 2.2 million m3; 1.47 million m3 of silt squeezing by blasting; a total of 67,000 m3 of C40 concrete. The project is from August 30th, 2008 to March 11th, 2011.

福建福清核电一期工程北护堤工程

【概要描述】北护堤总长度为1921米,为斜坡式抛石防波堤,地基采用水下爆破挤淤处理,底部宽度60米,上部宽度7米,施工水深7米,顶部为现浇防浪胸墙,内外侧护面人工护面块体(2t及3t扭王字块体),该工程堤心石共计220万方;爆破挤淤147万方;C40混凝土共计6.7万方。开、竣工时间:2008年8月30日至2011年3月11日。

Northern revetment project for Fujian Fuqing nuclear plant

The total length of the north dike is 1921m. It is a slope-type riprap breakwater. The foundation is formed by underwater silt squeezing by blasting. The bottom width is 60m, the upper width is 7m, and the construction water depth is 7m. The top is cast-in-place anti-wave breast wall, and the inner and outer surface protection is artificial armour blocks (2t and 3t accropode blocks). The core stones of the project is total 2.2 million m3; 1.47 million m3 of silt squeezing by blasting; a total of 67,000 m3 of C40 concrete. The project is from August 30th, 2008 to March 11th, 2011.

  • 分类:核电站工程
  • 作者:
  • 来源:
  • 发布时间:2019-05-29
  • 访问量:6

北护堤总长度为1921米,为斜坡式抛石防波堤,地基采用水下爆破挤淤处理,底部宽度60米,上部宽度7米,施工水深7米,顶部为现浇防浪胸墙,内外侧护面人工护面块体(2t3t扭王字块体),该工程堤心石共计220万方;爆破挤淤147万方;C40混凝土共计6.7万方。开、竣工时间:2008830日至2011311日。

Northern revetment project for Fujian Fuqing nuclear plant

The total length of the north dike is 1921m. It is a slope-type riprap breakwater. The foundation is formed by underwater silt squeezing by blasting. The bottom width is 60m, the upper width is 7m, and the construction water depth is 7m. The top is cast-in-place anti-wave breast wall, and the inner and outer surface protection is artificial armour blocks (2t and 3t accropode blocks). The core stones of the project is total 2.2 million m3; 1.47 million m3 of silt squeezing by blasting; a total of 67,000 m3 of C40 concrete. The project is from August 30th, 2008 to March 11th, 2011.

 

 

 

 

 

 

 