江苏田湾核电站5、6号机组大件码头港池及航道疏浚工程
- 分类:核电站工程
- 作者:小编
- 来源:
- 发布时间:2021-09-07
【概要描述】该工程码头前沿停泊水域面积0.36万㎡,回旋水域、连接水域、航道的面积为10.56万㎡。第一次清淤约为18万方,第二次清淤约为16.5万方,第三次清淤约为17万方,第四次清淤约为16.5万方。本工程2017年2月开工,工期近3年。
Jiangsu Tianwan Nuclear Power Plant Unit 5 & 6 Heavy Cargo Terminal Basin and Channel Dredging Works
The mooring area at the front of the wharf is 3,600 m2, and the area of the turning water area, connecting water area, and navigation channel is 105,600 m2. The first dredging of the port and navigation channel is about 180,000 m3, the second dredging is about 165,000 m3, the third dredging is about 170,000 m3, and the fourth dredging is about 165,000 m2. The project commenced in February 2017, with a construction period of nearly 3 years.
江苏田湾核电站5、6号机组大件码头港池及航道疏浚工程
【概要描述】该工程码头前沿停泊水域面积0.36万㎡,回旋水域、连接水域、航道的面积为10.56万㎡。第一次清淤约为18万方,第二次清淤约为16.5万方,第三次清淤约为17万方,第四次清淤约为16.5万方。本工程2017年2月开工,工期近3年。
Jiangsu Tianwan Nuclear Power Plant Unit 5 & 6 Heavy Cargo Terminal Basin and Channel Dredging Works
The mooring area at the front of the wharf is 3,600 m2, and the area of the turning water area, connecting water area, and navigation channel is 105,600 m2. The first dredging of the port and navigation channel is about 180,000 m3, the second dredging is about 165,000 m3, the third dredging is about 170,000 m3, and the fourth dredging is about 165,000 m2. The project commenced in February 2017, with a construction period of nearly 3 years.
- 分类:核电站工程
- 作者:小编
- 来源:
- 发布时间:2021-09-07
- 访问量:0
该工程码头前沿停泊水域面积0.36万㎡,回旋水域、连接水域、航道的面积为10.56万㎡。第一次清淤约为18万方,第二次清淤约为16.5万方,第三次清淤约为17万方,第四次清淤约为16.5万方。本工程2017年2月开工,工期近3年。
Jiangsu Tianwan Nuclear Power Plant Unit 5 & 6 Heavy Cargo Terminal Basin and Channel Dredging Works
The mooring area at the front of the wharf is 3,600 m2, and the area of the turning water area, connecting water area, and navigation channel is 105,600 m2. The first dredging of the port and navigation channel is about 180,000 m3, the second dredging is about 165,000 m3, the third dredging is about 170,000 m3, and the fourth dredging is about 165,000 m2. The project commenced in February 2017, with a construction period of nearly 3 years.